1) If A can
do a piece of work in n days, work done by A in 1 day = 1/n
2) If A does 1/n work in a day, A can finish
the work in n days
3) If M1 men
can do W1 work in D1 days working H1 hours per day and M2 men can do W2 work in
D2 days working H2 hours per day (where all men work at the same rate), then
(M1 D1 H1 / W1) = (M2 D2 H2 / W2)
4) If A can
do a piece of work in p days and B can do the same in q days, A and B together
can finish it in pq / (p+q) days
5) If A is
thrice as good as B in work, then
Ratio of
work done by A and B = 3 : 1
Ratio of
time taken to finish a work by A and B = 1 : 3
6) If A can do a work in ‘x’ days and B can do the same work in ‘y’ days, then the number of days required to complete the work if A and B work together is: (x*y)/(x+y)
7) If A can do a work in ‘x’ days and A + B can do the same work in ‘y’ days, then the number of days required to complete the work if B works alone is: (x*y)/(x-y)
Quantitative Aptitude & Data Interpretation
6) If A can do a work in ‘x’ days and B can do the same work in ‘y’ days, then the number of days required to complete the work if A and B work together is: (x*y)/(x+y)
7) If A can do a work in ‘x’ days and A + B can do the same work in ‘y’ days, then the number of days required to complete the work if B works alone is: (x*y)/(x-y)